Rebuild Update September 2014

Click an image to view a larger version.
Redevelopment Update - We hope to go to tender this month. Pray for the tender document which sets out what we want.

What we have done - We have obtained acoustic advice which has led to some changes to the surface finishes; We have developed the design of the servery for the concourse.

What’s coming up - Complete the tender document; Invite four contractors to submit a price to build our Church; Finalise the lease

Please pray for - Finalising the lease – that the council would not delay; For Ian Ford as he finalises the tender document; That we would receive good tenders